Workflow

  1. Obtain Permits & Approvals

    1-2 weeks

    Submit plans to local building department. Verify setback requirements, frost depth for footings, and railing height codes (typically 36 in for residential).

  2. Install Decking Boards

    1-2 days

    Start decking from the house outward, maintaining 1/8–1/4 inch gaps between boards. Use two screws per joist crossing, pre-drilling near board ends.

Tools Used

Checklist

0 / 7 completed

Loading your checklist…

Preparation

Framing

Foundation

Finishing

Reference Materials

Joist Span Table (Southern Pine, No. 2)Table

Maximum joist spans for common deck framing on residential decks.

Joist Size16 in OC12 in OC24 in OC
2×69 ft 11 in10 ft 10 in8 ft 4 in
2×812 ft 10 in14 ft 1 in10 ft 7 in
2×1016 ft 5 in18 ft 0 in13 ft 5 in
2×1218 ft 11 in21 ft 6 in15 ft 7 in
Deck Stain Coverage RatesTable

Approximate coverage for one coat on clean, dry decking.

Product TypeCoverage (sq ft/gal)Coats NeededDry Time
Transparent stain150–2501–224–48 hours
Semi-transparent200–3001–224 hours
Solid color stain250–3501–224 hours
Clear sealer200–3001–224 hours
Composite deck cleaner + sealer200–400112–24 hours
Frost Depth by RegionStandard

Footings must extend below the local frost line to prevent heaving. Common frost depths: Southern US 12 in, Mid-Atlantic 24–30 in, Midwest 36–42 in, Northern US/Canada 48–72 in. Always verify with local building code.

  • Ledger Board is Critical

    The ledger connection is the most common failure point. Use 1/2-inch lag screws (not nails) spaced 16 inches on center, with flashing above and below.

  • Composite vs. Wood Decking

    Composite decking costs 2–3× more upfront but eliminates annual staining. Factor maintenance time over 10 years when deciding.

  • Plan for Future Additions

    Install blocking for future pergola or shade sail attachment during framing — retrofitting is much harder after decking is installed.

  • Stain Before Railing

    Apply stain to decking before installing railing balusters — reaching between balusters afterward is tedious and produces uneven coverage.

Safety Notes

  • Decks over 30 inches high require guardrails by code — never skip railing on elevated decks.
  • Wear eye and ear protection when using circular saws and impact drivers; secure lumber before cutting.